You Get To Pay For Duke Plant At Edwardsport

Duke Energy
Duke Energy

If you are a Duke Energy customer, get ready to start paying for their extremely over budget power plant at Edwardsport.

The Indiana Court of Appeals has given Duke Energy the green light to raise electricity rates by 16%.

The coal gasification power plant was supposed to cost $1.9 billion but actually cost $3.5 billion when it was completed.

The court ruled unanimously Wednesday that you get to pay for that over the objections of environmental and consumer groups.

The Citizens Action Coalition says that they may appeal to the Indiana Supreme Court.